Construction Contracts in the UAE: FIDIC, the New Civil Code and Key Risks

A construction contract UAE parties sign onshore is a muqawala under the federal Civil Transactions Law, with mandatory rules such as decennial liability layered under amended FIDIC forms. Since 1 June 2026 a new code has changed the defaults on liquidated damages, hardship for lump sums, termination for convenience and defective work for contracts signed from that date.
Key pointFor contracts signed from 1 June 2026, hardship relief expressly reaches lump-sum contracts and cannot be excluded, so deleting the escalation clause no longer guarantees the employer a fixed price in exceptional market conditions.
At a glance
Muqawala under civil code
Onshore construction contracts are governed by the Civil Transactions Law's rules on contracting, which supply mandatory rules and defaults beneath the chosen standard form.
New code from June 2026
Federal Decree-Law No. 25 of 2025 took effect on 1 June 2026; most changes apply only to contracts entered into from that date.
Decennial liability retained
Contractors and architects remain strictly liable for collapse and structural defects, and the regime is substantively unchanged under the new code.
FIDIC is heavily amended
Most major projects use FIDIC Red, Yellow or Silver Books, but employers' particular conditions often reallocate ground, time and price risk.
Arbitration dominates disputes
Significant construction disputes are usually arbitrated, often at DIAC or seated in the DIFC or ADGM, with engineering experts playing a central role.
Swipe or scroll →
A construction contract UAE employers and contractors sign onshore is governed by the federal Civil Transactions Law, which treats it as a contract of muqawala and imposes rules the parties cannot contract out of, most notably decennial liability for structural defects. Most major projects use FIDIC forms, but they are heavily amended, and since 1 June 2026 a new Civil Transactions Law has changed the default rules on liquidated damages, hardship, termination and defects for contracts signed from that date.
This guide explains how construction contracts work in the UAE, how to choose a procurement route, the FIDIC amendments that shift the most risk, and the drafting points that the new code makes urgent. It reflects the position as of October 2026.
The short answer: what governs a construction contract UAE parties sign
Every construction contract UAE parties enter into onshore sits inside three layers:
- Mandatory law. The Civil Transactions Law regulates contracting (muqawala) and engineering services. Some of its rules, such as strict decennial liability of contractors and architects for collapse and structural defects, apply whatever the contract says.
- Default law. Where the contract is silent, the code supplies rules on variations, price, defects, termination and compensation. The new code, in force since 1 June 2026, changed several of these defaults.
- The contract. Standard forms, usually FIDIC-based, allocate design, time, price and risk. UAE courts and tribunals generally give effect to them, but read them through civil-law principles of good faith and judicial control of compensation.
Projects in the DIFC or ADGM, or contracts governed by DIFC or ADGM law, sit in a common-law environment instead. Licensing, permits and building regulation remain emirate matters handled by bodies such as Dubai Municipality and the relevant master developer.

The legal framework after 1 June 2026
The Civil Transactions Law issued by Federal Decree-Law No. 25 of 2025 replaced the 1985 code from 1 June 2026. Most of its changes apply only to contracts entered into from that date, so projects signed earlier continue under the old code for most purposes. Transitional rules apply to limitation periods that were still running on 1 June 2026, which makes claims diaries on legacy projects worth reviewing now. Our note on the new UAE Civil Transactions Law covers the general changes.
For construction, commentators have highlighted these shifts:
- Liquidated damages. The court's broad power to adjust agreed damages to actual loss has been replaced by specific grounds: reduction where the sum is exaggerated, where the obligation was partly performed, or where the employer's fault contributed; and increase where the contractor acted fraudulently or with gross fault.
- Hardship and lump sums. A lump sum still does not rise just because materials or labour cost more, but hardship relief now expressly reaches lump-sum contracts where exceptional, unforeseeable general circumstances upset the contract's balance. The court can extend time, adjust the price or rescind, and parties cannot contract out of that power.
- Termination for convenience. Where the contract is silent, an employer that ends the work early must pay for work done and expenses and also what the contractor could have earned, subject to deductions.
- Defective work. An employer can, in defined situations, rescind or hand the work to another contractor at the original contractor's cost without first applying to court.
- Notice of problems. A contractor must promptly notify the employer of defects in employer-supplied materials or other conditions impeding performance, or bear the consequences.
- Decennial liability. The regime is substantively retained, with clarification that the contractor's strict liability does not carry over automatically into its claims against subcontractors.
Disputes are usually resolved by arbitration under the Federal Law on Arbitration or in the onshore courts, which rely heavily on court-appointed engineering experts. Our pages on decennial liability in the UAE and force majeure and hardship go deeper on those regimes.
Choosing a procurement route and standard form
The first commercial decision is who designs. That choice drives the form, the price mechanism and where defects risk sits.
| Route | Typical form | Who designs | Price and risk profile |
|---|---|---|---|
| Traditional (design-bid-build) | FIDIC Red Book, often amended | Employer's consultant | Re-measured or lump sum; employer keeps design risk and most ground risk |
| Design and build | FIDIC Yellow Book | Contractor, to employer's requirements | Lump sum; contractor takes design and fitness-for-purpose risk |
| EPC / turnkey | FIDIC Silver Book | Contractor | Fixed price with most risk on contractor; suited to process and energy plant |
| Construction management | Bespoke or amended forms | Employer's team, packages let separately | Flexible; employer carries coordination and interface risk |
| Government projects | Emirate or authority standard forms | Varies | Terms largely non-negotiable; procurement rules apply |
Whichever route is chosen, the construction contract UAE parties sign should match the project's financing and insurance. FIDIC forms are familiar to international contractors and lenders, which is why they dominate. In the UAE, however, the earlier editions remain common alongside the current suite, and employers' particular conditions often run to many pages. The real contract is the amendments, not the published form.
Design responsibility and the designer's liability
Under UAE law, the designer and the contractor can be jointly liable for structural defects, and a supervising engineer may share liability for defects arising under its supervision. In design-and-build contracts, a fitness-for-purpose obligation can expose a contractor to liability beyond what its design consultant's professional indemnity insurance covers. Contractors should align their design subcontracts and insurance with the obligations they accept upstream.
FIDIC amendments that shift the most risk
Employers' amendments tend to follow familiar patterns. Each changes the risk allocation that FIDIC intended, and each now needs re-reading in light of the new code.
- Ground conditions. Transferring unforeseeable physical conditions to the contractor, sometimes with limited site investigation data.
- Time bars and notices. Tightening contractual notice periods and adding further conditions to claims. UAE tribunals have not always applied time bars strictly, and the new code's emphasis on good faith may encourage arguments against harsh enforcement.
- Liquidated damages. Higher rates and caps, or uncapped delay damages. Under the new code a contractor may argue for reduction on the specified grounds, while an employer may claim more on proof of fraud or gross fault.
- Price adjustment. Deleting escalation clauses. Contractors should note that hardship relief now applies to lump sums only in exceptional general circumstances, not market movements on one project.
- Liability caps and exclusions. Caps on liability are common, but the new code's prohibition on clauses that exempt or limit liability for harmful acts has raised a question about caps on tort-based claims.
- Payment and set-off. Extended payment periods, back-to-back payment terms in subcontracts and wide employer set-off rights.
Bonds, retention and insurance in a construction contract UAE projects use
Security packages are a frequent source of friction. A typical construction contract UAE employers issue asks for an advance payment guarantee, a performance bond and retention deducted from interim payments, with the bonds usually issued by UAE banks on demand terms. Contractors should negotiate the bond amounts, reductions as the advance is repaid, expiry dates tied to taking-over or the defects period, and an obligation on the employer to return them on time.
Insurance needs equal care. Contractors' all-risks cover, third-party liability and professional indemnity for design should match the obligations accepted in the contract, and decennial liability insurance is increasingly discussed for larger buildings. A gap between the risk accepted in the construction contract UAE parties sign and the cover actually bought is one of the most expensive mistakes on a project, because it only becomes visible after a loss.
Parent company guarantees deserve fresh attention. Under the new code a guarantor who is not jointly liable may require the creditor to pursue the principal debtor first. Employers taking parent guarantees on contracts signed from 1 June 2026 should draft them on a joint and several basis, or consider governing them by DIFC or ADGM law.
From tender to final account: the process
- Define the procurement strategy. Decide who designs, the price mechanism and the form, taking account of lender, insurer and authority requirements.
- Prepare and review the tender documents. Particular conditions, employer's requirements, specifications and bonds. Contractors should mark up the risk items rather than price them silently.
- Check licensing and authority. Confirm that the contractor and consultants hold the right licences and classifications, and that signatories have authority, including specific authority to agree to arbitration.
- Negotiate and sign. Agree bonds, insurances, liquidated damages and caps, and the dispute resolution clause, and make sure Arabic and English versions are consistent.
- Administer the contract. Issue notices on time, keep contemporaneous records, and treat variations and extension of time claims as they arise rather than at the end.
- Complete and hand over. Manage taking-over, defects notification periods and the release of retention and bonds.
- Close the final account. Settle the account and claims, and record any reservations before the relevant time limits expire.
Contractors new to the market should also check their own licensing; see our guide to licensing a contracting or engineering company in Dubai.
Illustrative scenario: a lump-sum contractor hit by a price spike
This scenario is illustrative only; the parties are generic.
A contractor signs an amended FIDIC Yellow Book lump-sum contract for a mixed-use building in July 2026. The employer has deleted the escalation clause. Six months later, regional disruption causes a sharp rise in the price of steel and other materials across the market.
Because the contract was signed after 1 June 2026, the new code applies. The contractor cannot claim more simply because costs rose. But if it can show the disruption was exceptional, general rather than project-specific, unforeseeable at signing, and so severe that it upsets the contract's financial basis, it may ask a court or tribunal to adjust the price or extend time, and the employer cannot rely on a clause excluding that power.
The contractor's position is much stronger because it notified the employer promptly, kept market price evidence and continued performing. The employer, for its part, uses the dispute to negotiate a shared-risk adjustment rather than litigate an uncertain hardship claim. The lesson for any construction contract UAE parties sign today is that price risk should be allocated expressly, because the statutory fallback is unpredictable.
Risks and common mistakes
Using pre-2026 templates without review
Many particular conditions were drafted around the 1985 code. Clauses that exclude the court's hardship power or restrict pre-contract disclosure are now ineffective for new contracts, and the default rules on termination, defective work and liquidated damages have changed. Employers and contractors should review their standard amendments, subcontract templates and guarantee forms before the next tender, rather than discover the gaps during a dispute.
Signing an arbitration clause without authority
UAE law treats agreeing to arbitrate as a significant act requiring proper authority. If the person who signed lacked authority to bind the company to arbitration, the other side may challenge the tribunal's jurisdiction or the award. Check the signatory's powers under the trade licence, articles or a specific power of attorney, and record them in the contract file. Our guide to DIAC arbitration in Dubai explains the procedure once a claim is filed.
Poor records and late notices
Construction disputes in the UAE are decided largely by experts reviewing documents. Contractors who cannot show when a delay started, what it affected and when notice was given struggle to recover time or money, however strong the underlying claim. Keep daily records, programme updates, correspondence logs and photographs, and issue notices within the contractual periods even where you expect to settle commercially.
Mismatched subcontract terms
Main contractors frequently accept obligations upstream that they do not pass down. Decennial liability, design responsibility, notice periods and liquidated damages should be mirrored in subcontracts where appropriate. The new code clarifies that the contractor's strict liability does not automatically flow into its claims against subcontractors, so recourse must be built into the subcontract wording and supported by evidence of fault.
Disputes and the cross-border angle
Most significant construction disputes in the UAE are arbitrated. In Dubai, the Dubai International Arbitration Centre is the main onshore institution, while Abu Dhabi has its own centre, and parties can seat arbitrations in the DIFC or ADGM. Onshore courts remain relevant for urgent relief and enforcement, and the DIFC Courts hear disputes where the contract or project falls within their jurisdiction. Our pages on construction disputes in the UAE and construction arbitration in the UAE compare the forums.
International contractors and consultants from the UK, China, India, Singapore and elsewhere often carry home-country standard terms and insurance assumptions. Those should be checked against UAE mandatory law: a cap or exclusion that works under English law may not survive decennial liability or the new code's limits. Bonds issued by foreign banks, parent guarantees and enforcement against assets abroad all need early planning.
What to do next
- Identify which of your live projects are under the old and new code.
- Review limitation periods on legacy claims in light of the transitional rules.
- Update FIDIC particular conditions, subcontracts and guarantee templates.
- Allocate price risk expressly in lump-sum contracts.
- Check signatory authority, especially for arbitration clauses.
- Strengthen notice and record-keeping procedures on site.
TRW & Co advises employers, contractors and consultants on construction contracts in the UAE, from procurement strategy and FIDIC amendments to claims and disputes. Where representation before the UAE courts is required, we work alongside locally licensed advocates. To review a contract or claim, contact our Dubai team.
Frequently asked questions
01Which law governs construction contracts in the UAE?
Onshore, construction contracts are governed by the federal Civil Transactions Law's provisions on contracting (muqawala) and engineering services, with specialist and emirate-level rules on licensing, permits and public procurement. A new Civil Transactions Law took effect on 1 June 2026 and applies to most contracts signed from that date. Contracts governed by DIFC or ADGM law, or projects within those centres, sit under their own common-law frameworks.
02Can decennial liability be excluded in a UAE construction contract?
Decennial liability is a mandatory regime under UAE civil law: contractors and architects are strictly liable for collapse and defects threatening a building's structural integrity for the statutory period, and the parties cannot simply contract out of it. The new code keeps the regime substantively unchanged while clarifying that the contractor's strict liability does not automatically transfer to its subcontractors. Insurance and back-to-back subcontract terms are the practical tools for managing it.
03Are FIDIC contracts enforceable in the UAE?
Yes. FIDIC forms are widely used and generally enforced, but they are read through UAE civil law. Mandatory rules such as decennial liability apply regardless of the contract, and courts and tribunals can adjust liquidated damages on statutory grounds. Employers usually amend the forms extensively, so the particular conditions matter more than the published text. Check that amendments work with the new Civil Transactions Law for contracts signed from 1 June 2026.
04Can a court reduce liquidated damages in the UAE?
Yes, but under the new code on narrower, specified grounds. For contracts signed from 1 June 2026, a court may reduce agreed damages where they are exaggerated, where the obligation was partly performed or where the employer's own fault contributed, and may increase them where the contractor acted fraudulently or with gross fault. Contracts signed earlier remain subject to the broader power under the 1985 code to align agreed damages with actual loss.
05What happens if an employer terminates a construction contract for convenience?
If the contract sets out what is payable, that usually governs. Where it is silent, the new code requires the employer to pay for work completed and expenses incurred, and also what the contractor could have earned had it finished, with deductions for savings and income from redeploying resources. FIDIC forms contain their own termination payment provisions, so check whether your amended conditions displace the statutory default.
06Where are UAE construction disputes resolved?
Most large disputes go to arbitration, commonly at the Dubai International Arbitration Centre, an Abu Dhabi institution, or with a DIFC or ADGM seat. Smaller disputes and claims without an arbitration clause go to the onshore courts, which appoint engineering experts to assess technical issues. The DIFC and ADGM Courts hear cases within their jurisdiction. The choice should be made at contract stage, with proper authority to agree to arbitration.
Sources and official materials
- Federal Decree-Law No. 25 of 2025 Promulgating the Civil Transactions Law — New civil code in force from 1 June 2026, including contracting rules
- Federal Law No. 6 of 2018 on Arbitration — Framework for arbitrating construction disputes onshore
- Dubai International Arbitration Centre — Main Dubai institution for construction arbitration
- FIDIC — Publisher of the Red, Yellow and Silver Book standard forms
- Dubai Municipality — Building permits and construction regulation in Dubai
- DIFC Courts — Common-law courts for DIFC-related disputes
General information only, current as at 27 October 2026. It is not legal advice and does not create a lawyer–client relationship. UAE law differs between the onshore jurisdiction, the DIFC, ADGM and the free zones, and changes frequently; check current official sources and take advice on the facts of your matter.